Scovell Estate repairs near completion after weeks without heating in Borough
Southwark Council expects the last 42 homes to be reconnected by the end of 14 October and will set out compensation once the work is complete.
EY says the expected overspend raises doubts about how the council sets its budget. Social care and temporary housing are behind most of the extra costs.
Tower Hamlets Council’s auditors have raised significant concerns about its worsening finances. The east London council expects to spend about £19m more than its budget this year.
EY set out the warning in a report to councillors at the council’s audit committee last week. The firm said the overspend was “not consistent with effective financial planning and budgetary control” and questioned how sound the assumptions behind the council’s budget were.
In July the council said it expected to go £19.2m over budget in the financial year that ends in March 2027. It spent £19.4m more than planned the year before.
Most of the extra spending comes from rising demand and higher costs in adult and children’s social care, along with temporary housing for homeless residents. Councils have a legal duty to provide these services.
Stephen Reid of EY told the committee that the auditors had not finished their review of the council’s financial management, but had already identified the decline. Chris Leslie, the council’s senior manager for strategic and corporate finance, said the overspends came from demand-led services and that the costs had built up late in the last financial year. “In children’s social care we have a high number of high complexity cases coming in at year-end,” he said. He added that cases which arrived near the end of the year had carried over into this one. He also said the council needed to review how it forecasts demand and costs so that it can set a sound budget in future years.
London Councils, which represents the capital’s local authorities, says the 33 councils face a combined shortfall of £5.2 billion by 2030.
Nine London councils are now propped up by the government’s Exceptional Financial Support scheme, which allows authorities in serious difficulty to borrow in an emergency so they can balance the books. The City of London, Lambeth, Croydon and Waltham Forest are on the list. So are Haringey, Barnet, Hillingdon, Redbridge and Havering. Tower Hamlets is not among them.
It expects to go £19.2m over budget in the financial year ending March 2027, after a £19.4m overspend the year before.
Rising demand and higher costs in adult and children's social care, plus temporary accommodation for homeless residents.
Its auditors, EY, in a report to the council's audit committee last week. EY said its review was still going on.
Southwark Council expects the last 42 homes to be reconnected by the end of 14 October and will set out compensation once the work is complete.
Venesha Rose says repairs to her Lambeth Council home failed to fix the cause, and she has been raising leaks with the council since 2024.
No control room record shows when a code blue was called after Aktar Uddin was found unresponsive in his cell on Christmas Day 2021.
Under the largest option, a Band D bill would reach £2,522.50 a year before the GLA precept. The council leader says protecting services comes first.
We use strictly necessary cookies to run the site and to remember this choice. With your permission we would also use analytics cookies, to count visits and see which stories are read, and advertising cookies, so the adverts that pay for How2London can be shown and measured. You can accept all, reject all, or choose for yourself. Read our cookie policy and privacy policy.
Needed for the site to work and to remember your cookie choice. Always on, no consent required.
Google Analytics 4 counts visits and shows which stories are read. Without consent it runs without cookies.
Google AdSense cookies, used to show and measure adverts. Our own How2London banners need no cookies and are shown either way.