Rails at platforms 5 to 8 will sit lower, so the train floor meets the platform edge and staff will not need to bring out ramps.
Passengers boarding Elizabeth line trains at the new Old Oak Common station will not face a step up. The government has signed off a redesign that drops the rails at the station’s four Elizabeth line platforms, so the floor of the train will be level with the platform edge.
The work covers platforms 5 to 8. Through the station, trains will run on a solid concrete slab instead of ballast.
National rail platforms are normally built 915mm above the rails. That height is a compromise that lets passenger, freight and engineering trains all use them, but at many stations it leaves a gap between train and platform. Old Oak Common was going up to that standard, which would have meant manual ramps for anyone needing step-free access to Elizabeth line trains.
The Elizabeth line’s central London stations avoided the problem in 2018, when the railway was granted a special exemption from the rules so its platforms could line up with the train doors. Old Oak Common is due to be the HS2 terminus. TfL expects Elizabeth line passengers to account for about 90 per cent of the people changing trains there. Serving that many with ramps would take a lot of staff and longer stops at the platform, and that would slow the service down.
Andy Lord, London’s Transport Commissioner, said level boarding was “vital for the safety and accessibility of our customers”.
TfL flagged the issue a few years ago and talks have continued since. In August an HS2 spokesperson said a fix had been found and was awaiting final approval. Building the platforms higher would have forced a redesign of the lifts, stairs and escalators. Dropping the railway instead means every platform, and the equipment that goes with it, can be built to one specification.
Signs are expected to send Elizabeth line passengers to platforms 5 to 8 and national rail passengers to platforms 1 to 4. Even so, the station was designed so any train can call at any platform. HS2 says compatible passenger and freight services on the relief lines will still be able to use the lowered platforms when required.
On those trains the carriage floor will sit below the platform edge, the reverse of most stations. Ramps are made for a train that is higher than the platform, so staff will offer passenger assistance whenever a GWR or Heathrow Express service calls at the Elizabeth line side. Such stops should be rare, for instance when engineering work closes a national rail platform.
Yes. The railway at platforms 5 to 8 is being set lower, so passengers can board Elizabeth line trains without a step or a ramp.
Higher platforms would have meant redesigning the lifts and other station equipment. Lowering the railway lets every platform be built to the same specification.
Compatible passenger and freight services can use them when required. Their floors will sit below the platform edge, and staff will offer assistance if GWR or Heathrow Express trains call there.
Cabinet voted unanimously for the C9 scheme, which adds three floating bus stops. A resident had urged councillors to reject it over safety.
Track work also closes part of the Weaver line for the weekend and shuts the Hertford East branch for nine days.
Places for London has finished converting 12 arches under the Jubilee and Metropolitan lines and is now looking for businesses to move in.
Two station assistants turned wasteland into a community garden. Public voting runs until Sunday 18 October, and the winner will be named on 20 October.
We use strictly necessary cookies to run the site and to remember this choice. With your permission we would also use analytics cookies, to count visits and see which stories are read, and advertising cookies, so the adverts that pay for How2London can be shown and measured. You can accept all, reject all, or choose for yourself. Read our cookie policy and privacy policy.
Needed for the site to work and to remember your cookie choice. Always on, no consent required.
Google Analytics 4 counts visits and shows which stories are read. Without consent it runs without cookies.
Google AdSense cookies, used to show and measure adverts. Our own How2London banners need no cookies and are shown either way.