Hammersmith Road cycleway to become permanent after council backs TfL’s £20m plan
Cabinet voted unanimously for the C9 scheme, which adds three floating bus stops. A resident had urged councillors to reject it over safety.
The final round of consultation on the £1.7bn line showed strong support, and building could begin by 2029.
Transport for London will seek legal permission early in 2027 to build a DLR branch from Gallions Reach to Thamesmead, with a new stop at Beckton Riverside. The decision follows a summer consultation on the £1.7bn line, the third and last, in which responses showed strong support for the plan.
A total of 553 responses came in, 527 from members of the public and 26 from stakeholder groups. Earlier rounds set out the broad scheme. This time the questions were about detail, such as the design of the two stations and the disruption building work would bring to people living nearby. TfL says it will use the answers to refine the scheme before it applies for a Transport and Works Act Order. That order, if granted, would approve the two stations and the route across the Thames.
Building could start by 2029, provided the Government signs a funding deal and the permissions come through. The first passengers could then travel in the early 2030s. The work would be paid for with borrowing, to be repaid over time from possible future direct Government funding and from new income generated by the line, such as fares on the new section.
TfL’s initial plan is a Thamesmead train, running via Beckton Riverside, every 8 to 10 minutes, with Beckton trains at the same frequency. On the shared stretch from Canning Town out to Gallions Reach, that adds up to a train every 4 or 5 minutes. Where Thamesmead services go after Canning Town will be settled closer to opening.
Some people feared the branch would weaken services on other parts of the network. TfL’s answer was that its 54 new DLR trains, now being rolled out, can cope with the extra passengers. Others wanted the line to carry on to Abbey Wood. TfL said that was unaffordable for now, and that adding another station in Thamesmead would affect the area too heavily.
Seb Dance, Deputy Mayor for Transport, pointed to the Government’s support for the plans in last year’s Budget. He said the line could “transform travel” in a part of London that has “historically lacked the public transport connections it needs”. Rachel Reeves, the former Chancellor, gave the project priority over others last November and said she expected it to unlock 30,000 new homes.
Lord Len Duvall, who represents Greenwich and Lewisham on the London Assembly, said he had campaigned for the extension for years. In his view it would shorten journeys and give Thamesmead a direct link into the wider network.
Separately, TfL is drawing up road changes along the route from Woolwich to Abbey Wood through Thamesmead, aimed at faster bus journeys and better conditions for walking and cycling. One proposal is a link joining the two ends of Barnham Drive that only buses, people on bikes and people on foot could use.
It could open in the early 2030s. Building could start by 2029 if a funding deal with the Government is agreed and permissions are granted.
Two new stations are planned, at Beckton Riverside and Thamesmead.
At first, TfL expects a Thamesmead train, running via Beckton Riverside, every 8 to 10 minutes.
TfL said taking the line on to Abbey Wood would be unaffordable for now.
Cabinet voted unanimously for the C9 scheme, which adds three floating bus stops. A resident had urged councillors to reject it over safety.
Track work also closes part of the Weaver line for the weekend and shuts the Hertford East branch for nine days.
Places for London has finished converting 12 arches under the Jubilee and Metropolitan lines and is now looking for businesses to move in.
Two station assistants turned wasteland into a community garden. Public voting runs until Sunday 18 October, and the winner will be named on 20 October.
We use strictly necessary cookies to run the site and to remember this choice. With your permission we would also use analytics cookies, to count visits and see which stories are read, and advertising cookies, so the adverts that pay for How2London can be shown and measured. You can accept all, reject all, or choose for yourself. Read our cookie policy and privacy policy.
Needed for the site to work and to remember your cookie choice. Always on, no consent required.
Google Analytics 4 counts visits and shows which stories are read. Without consent it runs without cookies.
Google AdSense cookies, used to show and measure adverts. Our own How2London banners need no cookies and are shown either way.